New HT Lines from EHV Substation - Nanded Circle
Status: Completed (31.03.2023)
Nanded Circle, Nanded Zone, Maharashtra, India
InfrastructureCompleted

New HT Lines from EHV Substation - Nanded Circle

This project involved constructing new 11 kV and 33 kV lines from a 132 kV Extra High Voltage (EHV) substation in Nanded Circle. The initiative enhanced the high-voltage transmission network, improving power reliability and capacity for industrial and residential consumers. Our team ensured precise installation, rigorous testing, and compliance with safety standards, contributing to a robust electrical infrastructure in Nanded Zone and supporting regional development.

Project Details

Work Order No: SE(Infra)/NDZ/Exp/235 Dt.15.12.2023
Year of Execution: 2022-2023
Value (Rs. Lakhs): 69.15
Category: Infrastructure